Renascor Purified Spherical Graphite Facility, Bolivar

The downstream half of Renascor Resources' vertically integrated Battery Anode Material project in South Australia: an operating Purified Spherical Graphite (PSG) demonstration plant, officially opened on 23 July 2026 and co-funded by an A$5 million Commonwealth grant under the International Partnerships in Critical Minerals Program, and the planned commercial-scale PSG facility at Bolivar, near Port Adelaide, covered by Export Finance Australia's conditionally approved A$185 million Critical Minerals Facility loan. Renascor's HF-free purification route combines sulfuric acid leaching with a low-temperature caustic bake and a reagent-recycling water treatment circuit, targeting battery-grade 99.95% carbon or better. One precision worth keeping: the demonstration plant is not on the Bolivar site — Renascor leased a 1,250 square metre industrial warehouse north of Adelaide, proximate to Bolivar, where it intends to build the full-scale commercial facility. No source loaded this pass states a tonnes-per-year capacity for either the demonstration plant or the commercial facility, so no capacity claim is recorded; the 60,000 tpa figure in Renascor's offtake framework is a non-binding sales volume, not plant capacity. The split of the commercial facility into separate purification and particle-shaping lines is inferred from the described conversion of graphite concentrate into Purified Spherical Graphite; no loaded source states the flowsheet order.

Facts on this page last re-verified Aug 12, 2026 — the oldest verification date among its current claims. How we verify.

Location: Bolivar, South Australia, Australia

Purification

PSG demonstration plant (HF-free purification)

Commissioned

Large-scale continuous Purified Spherical Graphite demonstration plant applying Renascor's HF-free purification process — sulfuric acid leaching with a low-temperature caustic bake plus a water treatment circuit that recycles reagents — producing battery-grade material for customer qualification and final technical validation. Housed in a leased 1,250 square metre industrial warehouse north of Adelaide, proximate to Bolivar, rather than on the planned commercial Bolivar site.

Material flow

Natural graphite concentrate → Uncoated spherical graphite

Capacity

No capacity claim. Absence of a figure means no source publishes one.

Qualification

No qualification claim. Status does not imply qualified output.

Purification

Commercial PSG facility purification (planned)

Financed

Purification stage of Renascor's planned commercial-scale Purified Spherical Graphite operation at Bolivar, South Australia, applying the HF-free sulfuric acid leach and low-temperature caustic bake process validated at the demonstration plant; pre-construction as of July 2026

Material flow

Natural graphite concentrate → Purified flake graphite

Capacity

No capacity claim. Absence of a figure means no source publishes one.

Qualification

No qualification claim. Status does not imply qualified output.

Particle processing

Commercial PSG facility particle shaping (planned)

Financed

Particle-shaping stage of the planned commercial Bolivar facility producing spherical graphite; the separation of shaping from purification within the flowsheet is inferred from the stated product (Purified Spherical Graphite) and is not described in any source loaded this pass

Material flow

Purified flake graphite → Uncoated spherical graphite

Capacity

No capacity claim. Absence of a figure means no source publishes one.

Qualification

No qualification claim. Status does not imply qualified output.