Facility

Graphinex Townsville Graphite-to-Anode Demonstration Facility

Graphinex's vertically integrated graphite-to-anode demonstration facility at Townsville, Queensland, described by the Queensland Government on 24 April 2026 as Australia's first facility to turn raw graphite into battery-ready material and as now operational. The plant runs on graphite mined and processed from Graphinex's Esmeralda project near Croydon in North West Queensland; the Crisafulli Government states it streamlined approvals to support the facility and declared the Esmeralda Graphite Project a Prescribed Project. The facility qualifies for this corpus on the processing-or-later basis as an Australian facility named in an official government source; the Esmeralda mine itself is excluded, because the only financing attached to it in the same statement is a US Export-Import Bank Letter of Interest, and non-binding letters of interest never qualify as government involvement. No capacity, purity or timeline figures appear in the statement, so none are recorded, and the internal split between purification and anode finishing is inferred from the 'vertically integrated graphite-to-anode' description rather than stated.

Facts on this page last re-verified Aug 12, 2026 — the oldest verification date among its current claims. How we verify.

Location: Townsville, Queensland, Australia

Purification

Demonstration graphite purification

Operating

Upstream processing stage of the vertically integrated graphite-to-anode demonstration plant, taking graphite mined and processed from the Esmeralda project through to battery-grade material; the statement does not describe the purification chemistry, and the split of the integrated demonstration plant into purification and anode-finishing lines is inferred from its description as vertically integrated graphite-to-anode

Material flow

Natural graphite concentrate → Purified flake graphite

Capacity

No capacity claim. Absence of a figure means no source publishes one.

Qualification

No qualification claim. Status does not imply qualified output.

Anode finishing

Demonstration anode material finishing

Operating

Downstream stage of the integrated demonstration plant producing battery-ready anode material described by the Queensland Government and by Graphinex as battery-grade; no coating or blending technology is named in the statement

Material flow

Purified flake graphite → Coated spherical purified graphite (CSPG)

Capacity

No capacity claim. Absence of a figure means no source publishes one.

Qualification

No qualification claim. Status does not imply qualified output.

Sources