Facility

Energy Fuels White Mesa Mill

Energy Fuels' White Mesa Mill in Blanding, Utah processes monazite into separated rare earth oxides alongside its uranium business. The Phase 1 circuit reached commercial production of separated NdPr in June 2024, and a commercial-scale heavy rare earth (Tb/Dy oxide) expansion began construction in July 2026, with a $725 million conditional loan commitment from the Department of War's Office of Strategic Capital announced in June 2026.

Facts on this page last re-verified Aug 11, 2026 — the oldest verification date among its current claims. How we verify.

Location: Blanding, Utah, United States

Separation

Phase 1 monazite-to-NdPr oxide separation circuit

Operating

Solvent-extraction separation of monazite into separated NdPr oxide; Phase 1 REE separation circuit completed Q1 2024

Material flow

Monazite Concentrate → NdPr Oxide

Capacity

1,000 t/year · Product mass · Nameplate · as of Jul 29, 2026

Qualification

No qualification claim. Status does not imply qualified output.

Separation

Heavy rare earth (Tb/Dy oxide) expansion

Under construction

Commercial-scale heavy rare earth oxide separation circuits (Tb and Dy) added to the existing mill separation flowsheet; sized for monazite concentrate feed from the Donald Project and third parties

Material flow

Monazite Concentrate → Dysprosium and Terbium Oxides

Capacity

20 t/year · Product mass · Target · as of Jul 29, 2026

120 t/year · Product mass · Target · as of Jul 29, 2026

Qualification

No qualification claim. Status does not imply qualified output.