Facility

Arafura Nolans Rare Earths Project

Arafura Rare Earths' Nolans project 135 km north of Alice Springs, Northern Territory, combining a rare earths mine with on-site beneficiation, extraction and separation plants targeting initial production of 4,440 tonnes per annum of NdPr oxide. Supported by a Northern Australia Infrastructure Facility loan of up to A$200 million and Export Finance Australia support comprising approximately A$140 million of invested equity and a debt commitment of up to A$700 million. Final investment decision announced 21 May 2026, with Arafura stating it would move to commence construction.

Facts on this page last re-verified Aug 11, 2026 — the oldest verification date among its current claims. How we verify.

Location: Nolans site, 135 km north of Alice Springs, Northern Territory, Australia

Mining & feedstock

Mining and beneficiation

Financed

Rare earths mine with on-site beneficiation plant producing a rare earth concentrate for the co-located extraction and separation plants

Material flow

Rare Earth Ore → Monazite Concentrate

Capacity

No capacity claim. Absence of a figure means no source publishes one.

Qualification

No qualification claim. Status does not imply qualified output.

Separation

Extraction and separation (NdPr oxide)

Financed

On-site extraction and separation plants producing separated neodymium-praseodymium oxide, targeting initial production of 4,440 tonnes per annum

Material flow

Monazite Concentrate → NdPr Oxide

Capacity

4,440 t/year · Product mass · Target · as of Jan 1, 2024

Qualification

No qualification claim. Status does not imply qualified output.